Files
vmux/.planning/STATE.md
Pierre Martin 399e3e8f02 docs(04-01): complete notifications et mode focus plan
- SUMMARY.md with execution results
- STATE.md updated (position, decisions, metrics)
- ROADMAP.md progress updated
- Requirements NOTIF-01, NOTIF-02 marked complete
2026-03-23 21:27:10 +01:00

94 lines
2.7 KiB
Markdown

---
gsd_state_version: 1.0
milestone: v1.0
milestone_name: milestone
status: Ready to execute
stopped_at: Completed 04-01-PLAN.md
last_updated: "2026-03-23T20:27:01.799Z"
progress:
total_phases: 4
completed_phases: 3
total_plans: 9
completed_plans: 8
---
# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-03-23)
**Core value:** Savoir instantanement quelle session Claude Code a besoin de moi, sans scanner manuellement mes workspaces.
**Current focus:** Phase 04 — notifications-et-i3bar
## Current Position
Phase: 04 (notifications-et-i3bar) — EXECUTING
Plan: 2 of 2
## Performance Metrics
**Velocity:**
- Total plans completed: 0
- Average duration: -
- Total execution time: 0 hours
**By Phase:**
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| - | - | - | - |
**Recent Trend:**
- Last 5 plans: -
- Trend: -
*Updated after each plan completion*
| Phase 01 P01 | 2min | 2 tasks | 5 files |
| Phase 01 P02 | 4min | 2 tasks | 8 files |
| Phase 02 P01 | 5min | 2 tasks | 5 files |
| Phase 02 P02 | 4min | 2 tasks | 7 files |
| Phase 03 P01 | 3min | 2 tasks | 4 files |
| Phase 03 P02 | 3min | 2 tasks | 5 files |
| Phase 04 P01 | 3min | 2 tasks | 9 files |
## Accumulated Context
### Decisions
Decisions are logged in PROJECT.md Key Decisions table.
Recent decisions affecting current work:
- Roadmap: CLI one-shot en Phase 1 (pas de daemon), daemon en Phase 2, hooks en Phase 3
- Roadmap: 4 phases derives des 4 categories de requirements
- [Phase 01]: procDir injectable pour testabilite (pas de /proc en dur)
- [Phase 01]: IdleThreshold = 60s (constante, configurable plus tard)
- [Phase 02]: WaitingSince gere par transition dans le registre, pas par le caller
- [Phase 02]: Scan initial synchrone avant socket listen (evite reponses vides)
- [Phase 02]: X11PIDResolver interface pour abstraire ewmh et tester sans X11
- [Phase 02]: maxPPIDDepth=20 pour securiser la remontee de chaine PPID
- [Phase 02]: Priorite fuzzy match : label > branche > cwd
- [Phase 03]: UpdateFromHook separe de Update: hooks ne connaissent pas PID/GitBranch/Preview
- [Phase 03]: WaitType omitempty pour compatibilite clients existants
- [Phase 03]: hookPort=0 dans tests pour eviter bind accidentel
- [Phase 03]: time.After dynamique remplace ticker fixe pour poll interval
- [Phase 04]: notify-send via os/exec avec timeout 5s (pas de lib D-Bus)
- [Phase 04]: Notification uniquement sur Working -> Needs Input (D-01)
- [Phase 04]: FocusTimer par timer uniquement, pas de toggle (D-04)
### Pending Todos
None yet.
### Blockers/Concerns
None yet.
## Session Continuity
Last session: 2026-03-23T20:27:01.792Z
Stopped at: Completed 04-01-PLAN.md
Resume file: None